Tentative Timeline for all Phases

Project PhaseStart PlanningStart Construction
Phase 210/163/18
Phase 310/173/19
Phase 410/183/20

Raw Water to Treatment Plant Pipeline

Phase StepsStart DateDate Completed
Conceptual  Design PhaseProgressingDone
Geotechnical ContractingProgressingDone
Easement AcquisitionProgressing Done
Preliminary DesignProgressing Done
Final Design11/15 Done
BiddingAwarded to Canyon Construction 7/11/16
ConstructionBy end of Sept. 2016.About 2/1/18

Domestic Water Phase 1

Phase StepsStart DateDate Completed
Walking Survey PermissionNow – ASAP Done
Preliminary DesignProgressing Done
Project Funding ActivitiesSubmitting to USDA Early June Done
Easement AcquisitionProgressing 
Collect Half the Tap FeeNow – 6/30/15 Done
Collect Remaining Half Tap Fee7/1/15 -12/31/15 Done
Final Design1/18Done
BiddingApril 2018 
ConstructionLate Spring or early summer 2018