Phase 0 Update

As of this time Phase 0 is making good progress. All of the 30” pipe from Lake Nighthorse to CR 210 is complete. 16” pipe is done from CR 210 to CR 141 except for a small section at the 210 & 141 intersection. Starting on Oct. 2 the 16” pipe will be put along CR 141 to CR 125. Traffic delays can be expected but probably won’t last more than a week. You also may have noticed powerlines going in along CR 210. Those are to supply power for the pump station at the lake. At this time Phase 0 should be completed in Jan. 2018.